Three things to know
- A fence or online map line may not define the exact on-site boundary.
- Clarify access, soil storage and working space separately.
- A land-use agreement does not replace design for protecting neighbouring structures.
Contents of this guide
Separate the boundary, fence and proposed excavation line
A fence is visible on site, but its position alone is not sufficient for a precise boundary-side work brief. Draw the known boundary and proposed intervention separately. State the basis of the boundary position and whether owners have clarified it.
ČÚZK notes that cadastral accuracy is not uniform. A line over an aerial photograph therefore does not replace necessary surveying information. If uncertain, discuss setting out or further steps with a specialist first, rather than moving a fence according to a screen.
On-site setting out also depends on the accuracy of recorded information. Give the surveyor existing documents and known uncertainties; booking a survey is not itself a reason to begin disputed work.
Clarify where work will actually take place
The scope extends beyond the trench. Mark equipment space, loading, temporary material storage and other contractors' movements. If any activity uses someone else's land, clarify conditions and authority for that use beforehand.
The agreement needs specific content: which location, activity and period. Give the contractor the secured arrangements and a contact. Do not resolve a boundary or access dispute by improvising when the excavator arrives.
Include neighbouring walls, ground and buried structures
Add surrounding walls, buildings, known foundations and level differences to the documents. Nearby structures may have functions not apparent from looking at the fence. The relevant designer or structural engineer must clarify technical effects in advance.
No universal setback or depth can make every intervention automatically acceptable. An access agreement does not replace technical work design either. Property issues, technical design and site arrangements are three different preparation tasks.
Prepare utility and handling information
Obtain available information and required utility marking along the work route. Mention private gate services, irrigation or old connections. Identify retained surroundings and any protection documents you already have.
Photograph the route from the road and entire working section. Where there is no soil storage space, handling and removal need another arrangement; space beyond a fence is not automatically available. Base the transport and work plan on genuinely secured space.
Swipe sideways to see all columns.
| Question | Information for the contractor |
|---|---|
| Where will work take place? | A plan with the boundary, route and known uncertainties |
| How will equipment arrive and where will handling occur? | Defined working space and clarified access conditions |
| What is nearby? | Documents for surrounding structures and the technical solution |
| What is underground? | Utility information and marking documents |
| What should remain afterwards? | Finishing scope and handover arrangements for affected areas |
Example: a trench beside an old fence
An owner wants a trench beside a fence with material placed on the other side. The initial enquiry lacks boundary documents, arrangements for neighbouring land and information on the wall foundation. Trench length alone therefore cannot establish a feasible plan.
Preparation first clarifies position, authority to use working areas and technical implications. Excavation and handling scope can then be agreed. This example shows missing information; it is neither execution instructions nor an actual SORTI reference.
What to write in the enquiry
Send the municipality, site plan, surroundings photographs and excavation purpose. State which areas are available, who supplies technical documents and whether neighbouring-property and access questions are resolved.
Add the preferred date, soil arrangements and target handover condition. Identify outstanding questions. Agreeing further preparation is more accurate than treating an incomplete brief as a finished order.
For the particular proposal, check required documents and any permissions with the designer or relevant building authority too. Being beside a fence alone establishes neither that permission is required nor that it is unnecessary.
Frequently asked questions
Can I position excavation using an online map line?
That may be insufficient for precise work beside a boundary. Cadastral accuracy varies; resolve required surveying information and uncertainties before working.
How many centimetres from a neighbour's fence can I dig?
There is no single generic distance. Structures, location, proposed work and clarified property arrangements all matter.
Is the neighbour's permission to drive through enough?
Supply the precisely clarified scope and land-use conditions. Access, soil storage and working space are different activities; technical design is assessed separately.
Can we discuss a quote while the boundary is still being resolved?
You can describe the intention and available documents. Final scope and execution must rely on a clarified position and the other conditions.