Foundation slab quotes: documents and scope of work

A foundation slab quote cannot be compared by footprint alone. The project, site conditions and included preparation and construction stages determine the scope.

Published · Updated · 3 min read

Start here

Three things to know

  • Compare the same project and scope.
  • Arrange service openings and interfaces before construction.
  • A slab price may exclude excavation and soil removal.
Contents of this guide
  1. Compare the same project and scope
  2. Separate groundworks from subsequent construction
  3. Complete a scope comparison table
  4. Check access for every stage
  5. Agree changes and handover before starting
  6. Example and a verified project reference

Compare the same project and scope

Attach the current project and list the work required. Identify excavation, soil handling, base preparation, service openings and slab construction to the design. SORTI undertakes foundation slabs to project documents; the actual scope is agreed for your site. Where documents are incomplete, the first discussion should identify missing information rather than replace the design.

Separate groundworks from subsequent construction

For excavation, distinguish preparation, digging, finishing, handling and loading. Define removal and receiving arrangements separately. Compare subsequent construction against the design and agreed result.

Allocate responsibility and coordination for penetrations, earthing, insulation and services. This list does not confirm that SORTI supplies every trade mentioned. It is a checklist for clearly allocating responsibilities between project participants.

Complete a scope comparison table

For each item, ask both contractors to confirm inclusion, quantities or charging method. “Included” must mean the same thing: removal including loading differs from transport of an already prepared stockpile.

Do not treat an empty field as an included item. If you arrange it yourself, specify how and when it connects. This table supports comparison; it is not a contract or technical design.

Swipe sideways to see all columns.

Working comparison checklist; each quotation confirms the actual scope.
AreaConfirm in both quotations
DocumentsDesign revision, levels and available ground information.
GroundworksExcavation, finishing and handling scope.
SoilRetained quantities, loading, removal and transfer.
Structure and layersSpecifically ordered work from the design.
Trades and coordinationResponsibility for penetrations, services and inspections.
Price and changesCharging method, VAT, exclusions and approvals.
HandoverRequired condition and responsible person.

Check access for every stage

Assess more than excavator access. Send photos and known restrictions for material deliveries and subsequent concreting. Width, turns, surfaces, standing space and handling matter. Each delivery method must suit the site.

Include temporary material storage and areas that must remain clear. Coordinate any space reserved by another trade. An address alone cannot confirm vehicle positioning or room for simultaneous deliveries.

Agree changes and handover before starting

Confirm who approves changes caused by different ground or unexpected obstacles, how they are recorded and priced. Handover of the excavation and required project inspections also matter. Individual stage acceptance belongs in the schedule.

Ask whether the price is fixed, estimated or based on actual work. Clarify VAT and exclusions. This guide gives no price per m²: without a confirmed scope and quotation, comparison could mislead.

Example and a verified project reference

Quotation A retains soil on site; quotation B includes loading and removal. Different totals in this illustrative case do not establish which work is cheaper. Align the required scope before comparing amounts.

Our Unhošť reference documents excavation for garage foundations. We do not describe it as a completed foundation slab. Explain whether you need groundworks or further work and send the current design. Confirm your quotation scope directly with Petr Mašín.

Frequently asked questions

Is the slab area enough for a quotation?

Not for a specific scope. Supply the design, site conditions and required work.

Does an excavation reference prove construction of the complete slab?

No. Use the documented scope: excavation alone does not establish a complete slab.

What if a contractor omitted an item?

Ask explicitly whether it is included, excluded or supplied by somebody else.

What if both contractors include the same follow-on task?

First agree who will actually provide it and in what scope. Request corresponding quotes rather than subtracting your own estimated amount.

Our work

See a completed project

Your next step

Send information for a comparable quotation

Attach the design and specify required work. Include the location, access photos and handover condition.